NR/L2/TRK/001/MOD13 ISSUE 5
Inspection & Maintenance of Permanent Way: Confirming track is Safe for Selected Linespeed after Work
| Organization: | NR |
| Publication Date: | 2 June 2012 |
| Status: | inactive |
| Page Count: | 7 |
scope:
This module applies when inspecting the line in order to:
a) Confirm that engineering work carried out under traffic has been safely completed;
b) Confirm that engineering work carried out when the line is blocked has been safely completed and the line is fit for traffic;
c) raise or remove an emergency or temporary speed restriction (ESR or TSR);
d) raise the permanent line speed (PSR).
This module does not apply to giving up line blockages or removing TSRs that have been imposed solely for the protection of staff.
Document History