scope:
This module applies when inspecting the line in order to:
a) confirm that engineering work carried out under traffic has been safely completed;
b) confirm that engineering work carried out when the line is blocked has been safely completed;
c) raise or remove an emergency or temporary speed restriction (ESR or TSR);
d) raise the permanent line speed (PSR).
This module does not apply when giving up line blockages or removing TSRs that have been imposed solely for the protection of staff.