scope:
This instruction applies to Trials, Acceptance, Commissioning, Fitting Out, Shakedown, and Post Shakedown Availability (PSA) of U.S. naval ships undergoing construction or conversion. Additionally, this instruction will normally apply to reactivations of units of the Inactive Fleet whenever reactivation involves modernization and/or conversion. In its application to nuclear-powered ships, it is augmented by reference (b). In its application to the Aircraft Carrier Service Life Extension Program (CV-SLEP), it is augmented by reference (c).
Document History